OGDCOrašje Green Data Center
A3 · E70 A1 · Vc A5 · Vc Orašje – Tuzla · ~61 km · planned Slavonski Brod Vinkovci Vukovar Županja Brčko Bijeljina Tuzla Gradačac ZAGREB · EU Belgrade SARAJEVO Croatia · EUBosnia & HerzegovinaSerbiaSava Orašje · OGDCDusine Business Zone0.5 → 2 → 5–10+ MW
Bosnia & Herzegovina · EU border region

OrašjeGreen Data Center

Green digital infrastructure at the gateway to the European Union

OGDC is investigating Orašje as the site for a modern, energy-efficient and secure data-center campus connecting Bosnia & Herzegovina with the EU market — built in phases, from pilot to regional campus.

Stage: pre-feasibility study
Conceptual view
0.5 MW
Pilot · concept
2 MW
Phase II · concept
5–10+ MW
Campus · concept
~1 km
to the EU border (Županja)
~12 km
to the A3 / E70 motorway
01The idea

A northern digital hub between Bosnia & Herzegovina and the European Union

Europe is short of grid capacity and fast-to-market data-center sites, while the region lacks modern, green and scalable digital infrastructure. OGDC is testing whether Orašje — right on the EU border, on the Sava, with 110 kV grid and European transport corridors — can answer both.

The strongest starting position is not “another hyperscale”, but a regional green edge, disaster-recovery and AI-ready campus that grows only after demand and infrastructure are confirmed.

01
EU gateway

Border location

Candidate zone next to the Orašje–Županja border crossing and regional transport corridors to the EU, BiH and the Western Balkans.

02
Energy

110 kV context

Transmission infrastructure is documented. Available capacity and redundancy remain subject to formal confirmation.

03
Growth

Modular campus

We start only with proven demand, with a clear path from pilot capacity to a multi-megawatt campus.

02Location

Orašje: on the EU border, at a crossroads of corridors

Verifiable site facts from official sources — the foundation of the investment case.

351,749 m²

of existing usable area in the Dusine Business Zone

VerifiedSource
~1 km

from the Orašje – Županja border crossing (HR / EU)

VerifiedSource
~12 km

to the Zagreb – Belgrade motorway (A3 / E70)

VerifiedSource
2 × 110 kV

corridors Brčko 1 – Orašje and Orašje – Županja (HR)

VerifiedSource
Regional study directionsZagreb / EUOsijekBrčkoBijeljinaTuzlaSarajevoBanja LukaBelgrade
Infrastructure in preparation · JP Autoceste FBiH

Orašje – Brčko – Tuzla motorway

The planned motorway of about 61 km will connect Tuzla Canton, Brčko District and Posavina via Orašje and the Sava bridge to the Croatian motorway network and the EU market. For OGDC this means a fast link between Orašje and the largest industrial and university centre of north-eastern BiH.

~61 km
total length
6
LOTs / sections
~KM 856.5m
earlier estimate, excl. VAT
13 bridges
on the first section
  1. LOT 1Orašje → Brčko~16 km to the Brčko District boundaryDesigner selected · 09/2026
  2. LOT 2Brčko → Maočasection through Brčko DistrictPlanned
  3. LOT 3Maoča → Majevicaapproach to MajevicaPlanned
  4. LOT 4A / 4BMajevica → Čanićimountain section across MajevicaPlanned
  5. LOT 5Čanići → Šićki Brod (Tuzla)~7.5 kmDesign documentation in progress

The project should be read as infrastructure in preparation; construction dates are not yet officially fixed. Official sources: FBiH Government · 2026 programme · FBiH Government · Orašje–Brčko District project

03Critical infrastructure

Power · Fiber · Resilience

Four things decide every data center. For each, we clearly separate what is documented from what still has to be proven.

PowerVerified
110 kV

Infrastructure identified in the official investment plan

CapacityUnder verification
1 / 2 / 5 / 10 MW

Formal connection options requested

FiberUnder verification
2+ routes

Target: physically independent carrier-grade routes

SiteUnder verification
Flood-safe

Engineering assessment and risk map required

OGDC does not claim available MW capacity, redundant feeds or cross-border carrier-grade fiber until documented by the relevant infrastructure operators.

04Energy & cooling

Green by design, not by slogan.

Grid + PPA

Reliable 24/7 foundation

The grid remains the primary continuous source; renewable power purchase agreements (PPAs) will be evaluated.

Solar + BESS

Local generation

Solar and battery storage are complementary assets — not a claim of 24/7 solar operation.

Cooling

Free cooling + liquid ready

Efficient air/free cooling and direct-to-chip readiness are the baseline. Using the Sava thermally remains a research concept.

05Modular campus

Growth in phases — only when demand is proven.

Each phase starts only when the previous gate has evidence: power, fiber, site and customers.

01
Phase I · Pilot 0.5 MW
40–100 racks
€5–7m≈ KM 9.8–13.7m
  • Colocation, DR and private cloud
  • Tier III design target
  • AI-ready zone and liquid-cooling readiness
02
Phase II · Regional 2 MW
150–400 racks
€17–25m≈ KM 33.2–48.9m cumulative
  • Enterprise, public sector, cloud
  • HPC and GPU capacity
  • Multiple carriers and power redundancy
03
Phase III · Campus 5–10+ MW
500–1,500+ racks
€45–90m+≈ KM 88–176m+
  • Hyperscale-ready campus
  • Sovereign / regional AI infrastructure
  • Expansion in line with available power
+
Option 20–50+ MW
  • Only if power, fiber, land and demand are proven

Conceptual capacities and indicative figures. Final sizing depends on grid availability, engineering, customer demand and financing.

06Investment opportunity

Indicative revenue and payback — 2 MW scenario

A working scenario for investor discussions. Figures are indicative and must be confirmed by the feasibility study, supplier quotes, connection terms and the final technical concept.

ScenarioUtilisationPriceStabilised revenue
Conservative60%€100 / kW / mo€1.44m / yr
Base75%€125 / kW / mo€2.25m / yr
Strong85%€150 / kW / mo€3.06m / yr
8–12+ yearsworking range for stabilised infrastructure payback; depends on CAPEX, utilisation, energy price, financing and service mix.

What goes into the real CAPEX

Land & siteGrid connectionSubstationShell & coreUPS / generatorsCoolingBESS / renewablesFiberSecurityProfessional feesContingencyIT / GPU — optional

Important: active server/GPU equipment, land, external power works and part of professional fees may be additional CAPEX. An AI/liquid-cooled design may increase construction cost.

07Market validation

The regional market exists. OGDC is finding its position.

Existing data centers in Zagreb, Serbia and BiH confirm real demand for colocation, cloud, HPC, business-continuity and disaster-recovery services. The goal is to prove whether Orašje can offer a different combination of location, power, connectivity, scalability and cost.

Zagreb / EU

Developed colocation ecosystem

Digital Realty publicly lists 3,100 m² of colocation space in Zagreb, 50+ cloud/network providers and 85+ customers — competition, but also proof of regional demand.

Digital Realty
Bosnia & Herzegovina

Cloud, HPC and DR already have a market

BH Telecom offers cloud in its own data centers, HPC, housing, private/hybrid/multicloud and business continuity including DRaaS and geo-redundancy.

BH Telecom
Belgrade / CEE

Regional interconnection hub

CETIN describes its carrier-neutral Belgrade data center as an interconnection hub for Serbia and CEE serving operators, financial institutions and digital services.

CETIN
Europe 2026

Demand is rising, power is the bottleneck

CBRE expects around 6.5% vacancy across European markets by end-2026 and more than 750 MW of new capacity; grid constraints and connection lead times remain key.

CBRE
Market signal from BiH

A 100 MW data center announced in Herzegovina

AAFS Infrastructure & Energy has publicly announced a 100 MW data-center development in Herzegovina, with a value reported in the media at around €530 million. OGDC tracks it as a market signal — not as a built facility or confirmed investment. If realised, it would show that BiH can attract large digital investments; Orašje positions itself as the northern EU-border hub, not a copy of it.

Status
Announced / development
Capacity
100 MW
Indicative CAPEX
≈ €530m
Location
Herzegovina

Why investigate Orašje?

  1. Directly on the EU / BiH border
  2. Greenfield space for phased development
  3. EU–BiH/CEE connectivity potential
  4. Grid + renewables + BESS concept
  5. Regional DR / business-continuity niche
  6. AI-ready design without depending on the AI market

Not yet proven: available MW, redundant power supply, two physically independent international fiber routes, flood and geotechnical suitability, the final plot, connection CAPEX and anchor demand. These are the key GO / NO-GO proofs.

Potential users

Banks & financePublic sectorHealthcareManufacturingRetailTelecomsSoftware / SaaSCloud providersAI / GPUBackup / DRRegional enterprisesContent / Edge

Target ecosystem

Categories and companies OGDC may address in the long term. They do not represent an existing partnership, interest or commitment by any company listed.

Hyperscale & cloudMicrosoft Azure · AWS · Google Cloud · Oracle Cloud · IBM · SAP
AI & accelerated computeOpenAI · Anthropic · NVIDIA · AMD · Meta
Network & edgeCloudflare · Akamai · regional carriers · IX / dark fiber
Industrial HPCRimac Group · automotive engineering · CAD / simulation · digital twins · universities
Anchor customersbanks · insurance · telecoms · public institutions · hospitals · ERP / SaaS · manufacturing
08Regional impact

What could OGDC mean for the region?

Planning scenarios, not forecasts or promises. They will be replaced by an economic-impact model as the study advances.

Permanent jobs

Pilot
8–15
Phase II
15–30
Campus
30–70
Scenario ranges — not forecasts.

Potential customer organisations

Pilot
15–40
Phase II
40–100
Campus
100–250+
Scenario ranges — not forecasts.
MetricPilotPhase IICampus
IT loadPreliminary0.25–0.5 MW1–2 MW5–10+ MW
Rack potentialPreliminary40–100150–400500–1,500+
Direct permanent jobsScenario8–1515–3030–70
Construction jobs (peak)Scenario30–8080–180200–500+
Potential active customersScenario15–4040–100100–250+
Local suppliersScenario5–15 firms10–30 firms20–50+ firms
1Orašje

Digital and power infrastructure, local procurement, skilled jobs and a potential technology cluster.

2Posavina Canton

Regional ICT capacity, resilience for businesses and public services, technical skills and supplier opportunities.

3Federation of BiH

Additional domestic cloud/DR capacity, digital-sovereignty options and infrastructure outside Sarajevo.

4Bosnia & Herzegovina

Cross-border digital infrastructure, keeping data in the country and a platform for cloud/AI investment.

5M-M-C d.o.o.

Project originator, local technology and integration partner, remote-hands/O&M and possible future SPV partner.

09Project status

Facts before promotion.

The project advances through gates. Every key claim must end as verified evidence — or as a reason for NO-GO.

  1. G0ConceptComplete
  2. G1Site & infrastructureIn progress
  3. G2Market validationPlanned
  4. G3Technical pre-feasibilityPlanned
  5. G4Financial modelPlanned
  6. G5Partners / anchor tenantPlanned
  7. G6Investment casePlanned
  8. G7Permitting & developmentPlanned

Evidence register

GO / NO-GO criteria

01Land

≥ 1–2 ha for pilot · 8–15+ ha for campus

02Power

≥ 1 MW for pilot · 10+ MW scalable

03Fiber

2 independent physical routes

04Risk

Flood, soil and environment cleared

05Demand

100–250 kW anchor pipeline

Due diligence: what we are formally verifying

A practical list for the City of Orašje, power utilities, telecoms, designers and investors. Every answer becomes evidence in the register.

01Land
  • Plot boundaries, access road, easements and room to expand
  • Phase I: 1–2 ha · Phase II: 3–5 ha · Phase III: 8–15+ ha (ideally a 20+ ha option)
  • Ownership, encumbrances, price/concession, plot assembly
  • Zoning, building ratios, space for substation, generators, BESS and solar
  • Geotechnics, bearing capacity and groundwater
02Power — priority #1
  • How many MW are available at the site today?
  • 1 MW for the pilot — by when? Then 3–5, 10, 20 and 50+ MW
  • Two physically independent feeds / N-1
  • Which substation and 110 kV lines, connection cost and lead time
  • Tariffs, PPA/renewables, own solar and BESS
03Fiber & network
  • Which carriers have fiber in the Dusine zone?
  • Exact routes and fiber ownership
  • At least two physically separate campus entries
  • 10/100/400 Gbit/s capacity and dark fiber
  • Latency to Zagreb, Sarajevo, Belgrade, Vienna and Frankfurt
04Water, cooling & environment
  • The Sava as a future heat source/sink — technically and legally
  • For the pilot: air/free cooling and closed-loop liquid cooling
  • Water permits, availability of process water
  • Waste-heat reuse
  • Generator and chiller noise
05Site risk
  • Official flood-risk map and historical Sava maximum
  • Plot elevation, embankment/platform raising, drainage
  • Seismicity, extreme temperatures, groundwater
  • Proximity to industrial and transport hazards
  • Emergency-services access
06Permits & timelines
  • Zoning approval and building permit
  • Environmental and water documentation
  • Power approvals and grid connection
  • Telecom rights of way
  • Customs treatment of IT and electrical equipment
07Market & anchor customers
  • Identify the first 100–250 kW of demand
  • Banks, insurance, public sector, hospitals, SaaS, telecoms, industry
  • Letters of intent (LOI), not just verbal support
  • SLA levels, rack density, certifications
  • Interest in DR, backup, private cloud, GPU/HPC
08Financing & partners
  • Equity, strategic investor, project finance or JV
  • EU/IFI and development funds, green and digital instruments
  • Energy, operating and telecom partner
  • Model: owner/operator, build-to-suit, wholesale or hybrid
  • Minimum pre-lease before construction starts

What global investors look at before deciding

CBRE · site selection

Power first, then scalability and network

  • Available power and scalability
  • Energy price
  • Multiple carriers and diverse routes
  • Planning certainty and risk
Source
OpenAI · site readiness

Powered land must be an executable project

  • Power, land, timing and cost
  • Permits and environmental constraints
  • Workforce and community support
  • A clear stage-gate plan
Source
Turner & Townsend · CAPEX

A CAPEX benchmark needs clear boundaries

  • Benchmark in US$/W of construction cost
  • Madrid and Dublin ~US$10/W (2025)
  • AI/liquid-cooled: +7–10% premium
  • Land and IT equipment excluded
Source
Market signal

Pre-leasing and anchor demand reduce risk

  • Do not build on assumed demand
  • Collect LOIs from regional customers
  • Define kW, SLA and rack density
  • Phases only with evidence from previous gates
Source
10Investor readiness

From concept to investment-ready project

OGDC is a pre-feasibility investment initiative. Technical options and development scenarios are not confirmed capacities, permits or contracted services.

Preliminary — not contracted

Partnership models

01

Powered shell / build-to-suit

Purpose-built facility aligned with an anchor customer’s requirements.

02

Wholesale colocation

Space, power and cooling for operators and larger customers.

03

Regional edge / AI-ready

Modular capacity for regional, disaster recovery and AI workloads, subject to demand.

Engineering workstreams

Power

Verify available MW, connection terms, N+1/2N options and backup generation.

Cooling

Compare dry, adiabatic and liquid cooling; model PUE/WUE and water demand.

Connectivity

Validate two physically diverse routes, carriers, latency and transport pricing.

Permitting & environment

Assess land title, floods, geotechnics, noise, emissions, water and environmental approvals.

Investment gates

  1. Verify site and land title
  2. Written grid and fiber operator responses
  3. Independent technical, financial and environmental assessment
  4. Customer interest (LOI) and phased financial model

Discuss a partnership

We welcome strategic investors, operators and potential customers to jointly validate feasibility.

Contact
11Partnership

Build the case with us.

OGDC is opening a structured dialogue with energy partners, telecom operators, data-center operators, infrastructure investors, development institutions, technology partners, anchor customers and the public sector.

Energy partnersTelecoms & carriersDC operatorsInvestorsDevelopment institutionsAnchor customersPublic sector